Construction of the Vrindavan Chandrodaya Mandir is steadily progressing. We would like to present the latest updates of the project.

 

  • Testing of  Piles
    • Testing of piles with load of 1800 tons using hydraulic equipment has been completed.

Project Status Update February 2016

  • Piling design for central tower (70m x 70m area) is completed.
    • The Central tower will have 285 piles. 189 of 55m depth & 96 of 52m depth, all of them 1m in diameter.

Project Status Update February 2016

  • 61 piles have been completed till date (57 in South & East wings, 4 in central tower portion).

Project Status Update February 2016

 

  • The  Raft  for the central 70m x 70m tower portion is approximately 3.5m deep (design work in progress).

 

Project Status Update February 2016 Project Status Update February 2016

 

  • Cost estimate for piles for central tower is Rs 25 Crores.

 

  • Cost estimate for raft for central tower is Rs 25 crores.

 

 

<<  Previous Project Report                         Project Status Update Gallery  >>




One thought on “Project Status Update February 2016

Leave a Reply

Your email address will not be published. Required fields are marked *